I-70 Bridges Project Update: Week of 5/31/2021
Below is a review of the work that has taken place on the project and work scheduled for the coming week:
Week of 5/31/2021
• I-70 Eastbound was closed from US 250 & WV 2 South - 16th Street Exit (Exit 1B) to the Oglebay Park Exit (Exit 2A) for phase two of the Fulton Bridge Replacement as part of the I-70 Forward Bridges Project.
o The US-250 North on-ramp to I-70 East was closed as a part of phase two.
o These closures are anticipated to continue until the end of September.
o All thru traffic is advised to use I-470 as the official detour to reach points East, while local traffic is encouraged to use US-40 Eastbound.
o Detours are posted in addition to maps that can be viewed on i70forward.com.
• There were alternating daytime single lane closures on Ohio Route 7 Northbound and Southbound through the I-70 overpass.
• The intermittent McColloch Street daytime closures continued.
• The left lane I-70 Westbound closure continued through all hours.
• Construction continued in Sections A and C Westbound where crossovers were in effect.
• The Market Street Overpass width reduction continued.
• The lane width reductions on the eastbound entrance ramp and westbound exit ramp to Wheeling Island continued.
• The on-ramp from Mount Dechantal Road to I-70 Eastbound was restricted to 12 feet wide in order to allow for substructure concrete bridge repairs.
Look Ahead to Week of 6/7/2021
• I-70 Eastbound will be closed from US 250 & WV 2 South - 16th Street Exit (Exit 1B) to the Oglebay Park Exit (Exit 2A).
o The US-250 North on-ramp to I-70 East will also be closed as a part of phase two.
o These closures are anticipated to continue until the end of September.
o All thru traffic is advised to use I-470 as the official detour to reach points East, while local traffic is encouraged to use US-40 Eastbound.
o Detours are posted in addition to maps that can be viewed on i70forward.com.
• The intermittent McColloch Street daytime closures will continue.
• The left lane I-70 Westbound closure will continue through all hours until the end of September.
• Construction will continue in Sections A and C Westbound where crossovers are in effect.
• The Market Street Overpass width reduction will continue.
• The lane width reductions on the eastbound entrance ramp and westbound exit ramp to Wheeling Island will continue.
• The width restrictions of the on-ramp from Mount Dechantal Road to I-70 Eastbound will continue in order to allow for substructure concrete bridge repairs.
• There will be nightly single lane closures on Ohio Route 7 Northbound and Southbound through the I-70 overpass. These will take place from 8 p.m. to 6 a.m. beginning on Tuesday, June 8 and continuing through Thursday, June 10.
Legal Disclaimer:
EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.