Project updates for the Week of April 5, 2021

TYLER – TxDOT is planning to conduct the following construction and maintenance work in the district during the Week of April 5, 2021. Work schedules are subject to change due to weather conditions, equipment failure, or other unforeseen issues. Slow down and pay attention in work zones.           

----------------------------------------

Anderson County – Palestine Maintenance plans to conduct edge repairs on SH 294 from Slocum to the county line. Expect lane closures utilizing a Truck Mounted Attenuator (TMA) for traffic control.

Anderson County construction projects updates:

County Road Off-System Bridge Project 

• Limits: Various locations in Anderson County

• Contractor: Stateline Construction, LLC 

• Cost: $1.5 million 

• Anticipated Completion Date: Summer 2021 

The contractor plans to work on the bridges and roadway elements for CR 458 and CR 468. The bridges on both roads are closed to thru traffic. The project is constructing bridges, and upgrading storm sewers, guardrails, base, pavement surfaces, and pavement markings.

 

US 79 Super 2 Project

• Limits: From 0.5-mile northeast of Loop 256 to the Anderson/Cherokee County line

• Contractor: Madden Contracting Company, LLC

• Cost: $14.4 million

• Anticipated Completion Date: Summer 2021

Work is ongoing on the shoulders and driveways, and to place drainage structures. The work zone speed limit is 60 mph. Expect lane closures and delays. The project is widening for a Super 2, and includes sub-grade work, surface treatment, base and surface hot-mix asphalt, widening structures, bridge rail, metal beam guard fence, signage, and permanent striping.   

----------------------------------------

Cherokee County – Jacksonville Maintenance plans to continue bridge work on the south end of the county. Base repairs will be conducted on FM 343 before moving to FM 1911 for a blade overlay project. Expect lane closures at all locations. 

Cherokee County construction projects updates:

US 84 Widening (New Project)

• Limits: From 0.43 mi east of SH 110 in Rusk, northeast to the Rusk County line in Reklaw

• Contractor: Madden Contracting Company, LLC

• Cost: $7.9 million 

• Anticipated Completion Date: Summer 2022

The contractor is scheduled to install work zone signs and begin right of way clearing. Expect lane closures and delays during construction. The project will widen and resurface the roadway, and add safety upgrades.

 

FM 235 Safety Widening 

• Limits: From SH 110 going east to FM 2274

• Contractor: Madden Contracting Company, LLC

• Cost: $3.5 million 

• Anticipated Completion Date: Fall 2021

The contractor is scheduled to continue installing drainage improvements. Expect lane closures with a pilot car managing traffic. The project will widen the existing roadway and incorporate safety upgrades.

 

FM 241 Safety Widening

• Limits: From US 69 going southeast to SH 21

• Contractor: A. L. Helmcamp, Inc.

• Cost: $5.5 million 

• Anticipated Completion Date: Summer 2021

The contractor is scheduled to perform cleanup activities. The project is widening the existing roadway and incorporating safety upgrades.

 

County Road Bridge Replacement Project 

• Limits: CR 2905 at Bowles Crk; CR 2614 at Beans Crk; CR 1504 at Turnpike Crk; CR 3203 at Mills Crk.

• Contractor: Stateline Construction, LLC

• Cost: $1.9 million

• Anticipated Completion Date: Spring 2021

No work is scheduled on CR 3203 and CR 1504. Both roadways are open to traffic. Construction of the new bridges is ongoing on CR 2905 and CR 2614. Both roads are closed to through traffic. The projects are replacing the existing bridges at each location with new structures.

 

SH 204 Super-2 Widening Project

• Limits: From US 79 in Jacksonville southeast to SH 110

• Contractor: Madden Contracting Company, LLC

• Cost: $13.7 million

• Anticipated Completion Date: Summer 2021

The contractor is doing earthwork, project seeding, and driveway repaving. Expect lane closures with a pilot car managing traffic. The project is adding passing lanes and includes safety upgrades.

 

US 69 Sidewalks in Jacksonville

• Limits: From Nacogdoches St. to Tena St. in Jacksonville

• Contractor: Highway 19 Construction, LLC

• Cost: $507,099.00

• Anticipated Completion Date: Spring 2021

No work is scheduled. The project is constructing sidewalks along US 69 in Jacksonville.

 

US 79 Widening Project

• Limits: From the Neches River to 1.2 miles northeast of FM 747

• Contractor: Drewery Construction Company, Inc.

• Cost: $8.2 million

• Anticipated Completion Date: Spring 2021

No work is scheduled. Expect delays during construction to widen the road and add passing lanes.

 

US 79 Rehabilitation Project

• Limits: From 0.16 mile east of SH 110 to the Mud Creek Relief Bridge

• Contractor: Madden Contracting Company, LLC

• Cost: $8.2 million

• Anticipated Completion Date: Spring 2021

The contractor is scheduled to place topsoil and perform guardrail work on the west end of the project. Expect lane closures and delays. The work zone speed limit is 60 mph. The project is rebuilding the roadway pavement and upgrading bridge rails.

----------------------------------------

Gregg County – Longview Maintenance plans to conduct pavement repairs Monday on US 80 near Hawkins Creek just east of SH 42 in White Oak. On Tuesday, work moves to Loop 281 near Tryon Road. Work returns to Loop 281 on Wednesday and Thursday from Spur 63 to Bill Owens Pkwy. Expect westbound closures Wednesday, and eastbound closures on Thursday. 

Gregg County construction projects updates:

FM 2206/Harrison Road 

• Limits: From Loop 281 to Fisher Rd

• Contractor: East Texas Bridge

• Cost: $15.16 million

• Anticipated Completion Date: December 2021

Work includes extending culverts and constructing detours. Expect lane closures and delays. The project consists of widening the two-lane road to four lanes with a center turn lane. Work includes drainage structures, flexible base, curb and gutter, sidewalks, hot mix, and pavement markings. 

 

FM 2206/Harrison Road 

• Limits: Fisher Rd to SH 42

• Contractor: East Texas Bridge

• Cost: $14.15 million

• Anticipated Completion Date: May 2022

The contractor will be extending culverts and constructing detours. Expect daytime lane closures and delays. The project consists of widening the two-lane road to four lanes with a center turn lane. Work includes drainage structures, a new bridge, flexible base, hot mix and pavement markings.  

----------------------------------------

Henderson County – Athens Maintenance plans to perform base repairs on FM 3441 between SH 31W and FM 59. A second crew will be blade laying hot mix on FM 2329 between FM 3054 and FM 316. Expect lane closures with flaggers providing traffic control at both locations.

Henderson County construction projects updates:

Safety Improvement Project 

• Limits: SH 31, etc.,  in Anderson and Henderson counties

• Contractor: 3LW Civil, LLC

• Cost: $1.4 million 

• Anticipated Completion Date: Summer 2021 

The contractor is scheduled to work on roadways in Anderson County. Expect lane closures and delays. The project will replace guardrail on various roadways in Henderson and Anderson counties.

 

Traffic Signal Project

• Limits: Various Locations in Henderson County

• Contractor: Texas Traffic Control Systems, Inc. 

• Cost: $1.0 million

• Anticipated Completion Date: Fall 2021

The contractor is scheduled to continue signal work on Loop 256 in Palestine. Expect lane closures and delays. The project consists of improving the intersection and installing a signal.

 

FM 59 Safety Improvements Project 

• Limits: From BS19J in Athens going southwest to Loop 7 

• Contractor: Big Creek Construction, LTD.

• Cost: $1.7 million 

• Anticipated Completion Date: Fall 2021 

The contractor plans to work on the roadway elements of FM 59. Alternate routes are required. The contract includes grading, asphalt concrete pavement base, base repair, one course surface treatment, concrete pavement surface and markings, metal beam guard fence, structures, signs.

 

US 175 Widening Project 

• Limits: From Loop 7 to FM 804

• Contractor: Reynolds & Kay, LTD 

• Cost: $12.1 million

• Anticipated Completion Date: Summer 2021

The contractor is scheduled to continue road work on the eastbound lanes. The work zone speed limit has been reduced to 60 mph. Watch for trucks entering and exiting the lane closure. The project consists of adding shoulders and improving drainage.

 

SH 334 Bridge Project

• Limits: From Knob Hill in Seven Points (one mile east of SH 274), east to Southland in Gun Barrel City (2.5 miles west of SH 198)

• Contractor: Austin Bridge and Road Services, LP

• Cost: $41.2 million

• Anticipated Completion Date: Spring 2021

The contractor is scheduled to continue work on the eastbound roadway elements. Expect lane closures and delays. The project will upgrade the road from two to four lanes and includes the construction of bridges, storm sewers, guardrails, base, pavement surfaces and markings.

----------------------------------------

Rusk County – Henderson Maintenance plans to continue hot mix overlay operations on FM 348 between US 79 and FM 1798. Bridge repairs are ongoing on various farm-to-market roads in the northwestern corner of the county including FM 2089, FM 838, and FM 2012. Expect lane closures with flaggers managing traffic at all locations.

Rusk County construction projects updates:

Landscape Improvement Project

• Limits: Numerous locations on US 79 and SH 64 in Rusk County

• Contractor: Tightline Construction 

• Cost: $172,300.00

• Anticipated Completion Date: April 2021

The project consists of landscape beds and scenic enhancement at numerous locations along US 79 south through town, SH 64, the intersection of US 259 and SH 322, and at the SH 64/SH 43 and US 79 intersection. The contractor will be working adjacent to the curb.

----------------------------------------

Smith County – Tyler Maintenance plans to continue bridge work on US 69 at Black Fork Creek. Shoulder-up work will continue on FM 344 between US 69 and FM 756. Expect lane closures at both locations with traffic managed by flaggers. Fog seal operations will be conducted on SH 64 from just east of Chapel Hill to FM 3226, if time allows. Lane closures will be implemented with a pilot car and flaggers. 

Smith County construction projects updates:

US 69 Overpass at FM 346

• Limits: At FM 346

• Contractor: Longview Bridge & Road, LTD.

• Cost: $16.7 million

• Anticipated Completion Date: Spring 2021

The contractor is scheduled to perform roadway reconstruction on FM 346 and ramp work. The work zone speed limit on US 69 is 60 mph. The project includes building a new US 69 bridge over FM 346. 

 

Guardrail Upgrades 

• Limits: At various locations in Smith and Cherokee counties

• Contractor: 3LW Civil, LLC

• Cost: $833,000.00

• Anticipated Completion Date: Spring 2021

The contractor is scheduled to conduct wrap-up activities. The project includes safety improvements including guardrail upgrades. 

 

FM 344, etc., Safety Improvements 

• Limits: FM 344 – From FM 756 east to SH 110; FM 768 – from Loop 456, S to FM 22

• Contractor: A R Brothers Construction Services, Inc.

• Cost: $1.8 million

• Anticipated Completion Date: Fall 2021

The contractor is scheduled to continue drainage improvements on FM 344. Work also continues to replace driveway pipes on FM 768. Expect lane closures during this work. The project consists of improving drainage, culvert work, and guardrail upgrades. 

 

US 69 (Broadway Ave.) Resurfacing Project 

• Limits: From 4th St. to Loop 323

• Contractor: Drewery Construction Co. Inc.

• Cost: $2 million

• Anticipated Completion Date: Spring 2021

No work is scheduled for the week. When in progress, work is slated from 8 p.m. to 6 a.m., Monday – Thursday, and on Sunday from 9 p.m. to 6 a.m. Expect lane closures and delays. The project consists of bridge rail and pavement resurfacing. 

 

Old Sabine River Bottom WMA Park Road Culvert Replacement (Notice of Project Completion)

• Limits: At Old Sabine River

• Contractor: Baker & Company Construction, LLC

• Cost: $178,000.00

• Anticipated Completion Date: Spring 2021

The project is complete. 

 

Sidewalks at Various Locations in Smith County 

• Limits: SH 64 in Tyler (Entrada Lane to Parkdale Drive); SH 110 in Troup (CR 2138 to FM 347); SH 135 in Troup (FM 13 to Tiger Drive)

• Contractor: Highway 19 Construction, LLC

• Cost: $3.5 million

• Anticipated Completion Date: Fall 2021

Sidewalk and driveway construction continue on SH 64 west of Loop 323 with daily lane closures. The project will construct sidewalks along SH 64W in Tyler, SH 110W in Troup, and SH 135N in Troup.

 

I-20 Resurfacing Project

• Limits: From FM 849 to 0.8 mile west of US 69

• Contractor: Texas Materials Group, Inc.

• Cost: $3.2 million

• Anticipated Completion Date: Spring 2021

No work is scheduled. When work is in progress, the schedule is from 8 p.m. to 6 a.m., Sunday through Thursday. Expect lane closures. The work zone speed limit is 65 mph. The project consists of ramp improvements and frontage road construction. 

 

FM 16, etc., Safety Improvements 

• Limits: From SH 155 to US 271

• Contractor: Stateline Construction, LLC

• Cost: $3.88 million

• Anticipated Completion Date: March 2021

The contractor is working on drainage upgrades and driveways. Expect lane closures and delays. The project consists of culverts, safety end treatments, drainage upgrades, bridge rail upgrades, new metal beam guard fence, and driveway asphalt.  

 

Loop 323 Resurfacing Project 

• Limits: From 0.1 mile west of SH 155, east to 0.8 miles east of US 69 in Tyler

• Contractor: Drewery Construction Co. Inc.

• Cost: $5 million

• Anticipated Completion Date: Spring 2021

No work is scheduled. When in progress, work hours are 8 p.m. to 5 a.m., Sunday through Thursday. The project consists of pavement resurfacing.

 

SH 135 Widening Project

• Limits: From Arp to Troup

• Contractor: Drewery Construction Co. Inc.

• Cost: $9 million

• Anticipated Completion Date: Fall 2021

The contractor is scheduled to continue surface paving operations. Expect lane closures with a pilot car managing traffic control. The work zone speed limit is 45 mph. The project is adding passing lanes, improving drainage structures, and pavement resurfacing.

 

I-20 Ramp Improvement Project

• Limits: From US 69 to Jim Hogg Road

• Contractor: Longview Bridge and Road, LTD

• Cost: $14.8 million

• Anticipated Completion Date: Summer 2021

No work is scheduled. The project consists of ramp improvements and the construction of frontage roads.

 

FM 2493 Widening Project

• Limits: From FM 2813 in Gresham south to FM 346 in Flint

• Contractor: Highway 19 Construction, LLC

• Cost: $14.5 million

• Anticipated Completion Date: Fall 2021

The contractor is scheduled to move traffic to the northbound lanes (east side of the road) and start surface paving on the southbound lanes. The work zone speed limit is 45 mph. The project is widening FM 2493 from two lanes to a four-lane divided roadway with a flush median. 

----------------------------------------

Van Zandt County – Canton Maintenance plans to conduct base repairs and level-up/overlay on FM 47 between I-20 and SH 243 in preparation for Summer Seal Coat. Expect lane closures with flaggers managing traffic control. A second crew will be performing bridge repairs on roads around Van Zandt County. No traffic impacts are expected but lane closures and flaggers will be implemented if needed.

Van Zandt County construction projects updates:

I-20 Metal Beam Guard Fence Improvements (New Project)

• Limits: SH 19 in Canton east to MLK Blvd. in Longview (Van Zandt, Smith, Gregg counties)

• Contractor: Sefbo Pipeline Bridge, Inc.

• Cost: $3.5 million

• Anticipated Completed Date: December 2021

Crews will be removing and replacing metal beam guard fence (MBGF) in Van Zandt County near SH 19 in the eastbound mainlanes. Expect lane closures to be in effect nightly managed by message boards and channelizing devices. The project is constructing safety improvements including MBGF and mow strip. 

 

I-20 Overlay Project

• Limits: From SH 64 in Canton to FM 314 in Van

• Contractor: Austin Bridge and Road Services, LP

• Cost: $5.2 million

• Anticipated Completion Date: April 2021

The project is substantially complete with crews addressing punch list items. No lane closures are anticipated. The project includes paving improvements in the westbound lanes from 1.6 miles east of FM 16 in Van to 0.4 miles west of FM 17 in Canton. The project includes pavement repair, planing, membrane underseal, permeable friction course (PFC) surface overlay, metal beam guard fence and pavement markings. The work zone speed limit is 65 mph.

 

Safety Improvement Project 

• Limits: FM 47 and other roads in Van Zandt, Anderson, Henderson and Smith counties

• Contractor: Highway 19 Construction, LLC

• Cost: $4.5 million 

• Anticipated Completion Date: Spring 2022 

Driveway and drainage structure work is ongoing on FM 47. Expect lane closures and delays. Project work includes grading, structure work, guardrail replacement, and bridge rail upgrades.

 

US 80 Safety Improvements

• Limits: From the Kaufman County line east to SH 19

• Contractor: Baker & Company Construction, LLC

• Cost: $2.54 million

• Anticipated Completion Date: April 2021

Crews will be addressing punch list items. Expect periodic outside lane closures managed with channelizing devices. The project is improving drainage, culverts, and upgrading guardrails for safety. 

----------------------------------------

Wood County – Mineola Maintenance plans to maintain bridges on US 80 eastbound at Lake Fork Creek. Expect lane closures. Hot mix overlay operations are planned for SH 182. Expect lane closures with a pilot vehicle managing traffic control.  

Wood County construction projects updates:

FM 14 Mill & Inlay 

• Limits: From FM 1795 (Hawkins) south for 4.3 miles to FM 2015

• Contractor: East Texas Bridge, Inc.

• Cost: $4.3 million

• Anticipated Completion Date: April 2021

Crews will be addressing punch list items. Expect various short duration lane closures managed by flaggers and directional devices. The project includes pavement repair, planing, Superpave base, membrane underseal, Superpave surface, metal beam guard fence, and pavement markings.

                  ----------------------------------------

I-20 Total Maintenance Contract

• Limits: Gregg, Smith and Van Zandt counties

• Contractor: Firemen Excavation, maintenance activities

• Contractor: Andrews Diversified Industries, litter removal 

Routine maintenance activities on I-20 are ongoing throughout the week with moving operations.

• Debris Removal/Pothole Repair Inside Lanes: Thursday through all counties

• Debris Removal/Pothole Repair Outside Lanes: Mon. - Wed. in all counties 

• Debris Removal/Pothole Repair Frontage Roads/Ramps: Friday in all counties

• Guardrail/Sign Repair: Emergency repairs due to vehicle crashes in all counties

• Tree Removal/Trimming: In Gregg County

• Sweeping Operations: Ongoing through all three counties

• Striping: Van Zandt County from FM 1255/Mile Marker 530 going east into Smith County

• Bridge Repair Follow-up: Gregg, Smith, and Van Zandt counties