ASPHALT RESURFACING OF RAMPS AND SHOULDERS

For Immediate Release:  Thursday, August 27, 2020 Contact: Rod Gall, Greg Rothschadl, or Nathan Schulte,(605)668-2929

 

NORTH SIOUX CITY, S.D. – The South Dakota Department of Transportation says asphalt concrete resurfacing of the inside shoulders of the north and southbound lanes of Interstate 29 from the Iowa line north to mile marker 5.0 will begin on Monday, Aug. 31. 

An asphalt concrete overlay will be also be placed on the ramps at Exits 2 and 4. Durable pavement markings will be placed once paving is complete. 

Lane closures will be set up on I-29 and exit ramps will be paved one-half width at a time so traffic can be maintained. 

Motorists can expect reduced speeds and are asked to be aware of suddenly slowing and merging traffic, as well as construction workers and equipment adjacent to the driving lane. 

The completion date for this project is Oct. 23, 2020. 

Knife River Midwest, LLC from Sioux City, Iowa, is the prime contractor on this $1.3 million project. 

For complete road construction information, visit https://www.safetravelusa.com/sd/ or dial 511.

 

- 30 -

Legal Disclaimer:

EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.