Roadwork Updates
Vinagro Materials will be performing asphalt binder layer and sidewalk installation. Tomorrow, Sept 4th, a binder layer of asphalt will be placed on Beech Rd, Linden Rd & Azalea Rd.
Starting Tuesday, Sept 7th, their concrete crew will be on Rockland St to start forming the sidewalks. They will be pouring concrete on Thursday, 9/10, Friday 9/11 and into next week. This work is weather dependent.
Legal Disclaimer:
EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.