PennDOT District 4 Road Report for the Week of October 31 to November 4, 2022
10/28/2022
Dunmore, PA - Below you will find the road report for the week of October 31 – November 4, 2022. The first set of information is our short-term projects and standard-of-care maintenance projects. The second set of information is our long-term projects which will be updated as work within the project changes.
Please note: Work will depend on current weather conditions.
Special Events
There will be a road closure on SR 2049 (Birkbeck Street, Front Street, and Centre Street) in Hazel Township, Luzerne County on Friday, October 28 for the Freeland Elementary School Halloween Parade from 12:30 PM to 2:00 PM.
There will be a road closure on SR 3025 (200 block of Wyoming Avenue) Scranton, Lackawanna County on Saturday, October 29 for an Enchanted Trunk and Treat from 2:00 PM to 5:00 PM.
There will be a road closure on SR 11, Shickshinny, Luzerne County on Sunday, October 30 for the annual Halloween Parade from 4:30 PM to 5:15 PM.
Short Term Projects
| Lackawanna County | | ||||
| State Route/Exit | Township | Closure/Restriction | Work | Dates | Time |
| I-81 | Lackawanna County | Lane Restriction | Deck Patching | 11/4 | 7:00 AM - 3:00 PM |
| I-81 | Lackawanna County | Lane Restriction | Brushing | 11/3 | 7:00 AM - 3:00 PM |
| I-81 Exit 194 to Exit 206 | Lackawanna County | Lane Restriction | Pothole Patching | 11/2-12/2 | 7:00 AM - 3:00 PM |
| 6 | Lackawanna County | Lane Restriction | Brushing | 11/1-11/4 | 7:00 AM - 3:00 PM |
| 307 | Clarks Summit Borough | Lane Restriction | Litter Pickup | 10/31-11/3 | 7:00 AM - 3:00 PM |
| 407 | Dalton Borough | Lane Restriction | Brushing | 11/4 | 7:00 AM - 3:00 PM |
| 348 | Elmhurst Township | Lane Restriction | Crack Sealing | 10/31 | 7:00 AM - 3:00 PM |
| 435 | Elmhurst Township | Lane Restriction | Crack Sealing | 10/31 | 7:00 AM - 3:00 PM |
| 435 | Lackawanna County | Lane Restriction | Deck Patching | 11/4 | 7:00 AM - 3:00 PM |
| 524 | North Abington Township | Lane Restriction | Patching and Cutting | 11/2 | 7:00 AM - 3:00 PM |
| 590 | Lackawanna County | Lane Restriction | Pipe Replacement | 11/1-11/4 | 7:00 AM - 3:00 PM |
| 590 | Lackawanna County | Lane Restriction | Ditch Cleaning | 11/1-11/4 | 7:00 AM - 3:00 PM |
| 690 | Moscow Borough | Lane Restriction | Crack Sealing | 11/1-11/4 | 7:00 AM - 3:00 PM |
| 1001 | Vandling Borough | Lane Restriction | Patching and Cutting | 10/31-11/1 | 7:00 AM - 3:00 PM |
| 1003 | Fell Township | Lane Restriction | Ditch Cleaning | 11/3-11/4 | 7:00 AM - 3:00 PM |
| 1003 | Fell Township | Lane Restriction | Patching and Cutting | 11/2-11/4 | 7:00 AM - 3:00 PM |
| 1006 | Scott Township | Lane Restriction | Pipe Replacement | 11/1 | 7:00 AM - 3:00 PM |
| 1012 | Archbald Borough | Lane Restriction | Pipe Replacement | 10/31 | 7:00 AM - 3:00 PM |
| 1101 | Lackawanna County | Lane Restriction | Joint Repair | 10/31-11/3 | 7:00 AM - 3:00 PM |
| 2004 | Madison Township | Lane Restriction | Crack Sealing | 11/1-11/4 | 7:00 AM - 3:00 PM |
| 3012 | Old Forge Borough | Lane Restriction | Brushing | 10/31 | 7:00 AM - 3:00 PM |
| 3012 | Taylor Borough | Lane Restriction | Brushing | 10/31-11/2 | 7:00 AM - 3:00 PM |
| 3016 | Taylor Borough | Lane Restriction | Litter Pickup | 11/3-11/4 | 7:00 AM - 3:00 PM |
| Various | Lackawanna County | Lane Restriction | Joint Repair | 10/3-11/3 | 7:00 AM - 3:00 PM |
| Various | Lackawanna County | Lane Restriction | Sign Review | 11/1-11/4 | 7:00 AM - 3:00 PM |
| Various | Lackawanna County | Lane Restriction | Sign Repairs | 10/31 | 7:00 AM - 3:00 PM |
| | | | | | |
| Luzerne County | |||||
| State Route/Exit | Township | Closure/Restriction | Work | Dates | Time |
| I-81 NB Exit 151(A) to Exit 151(B) | Luzerne County | Lane Restriction | Boring and Bridge Deck Cores | 10/24 -11/4 | 8:00 PM - 6:00 AM |
| I-81 NB & SB Mile Post 164.3 | Luzerne County | Lane Restriction | Deck Repair | 10/30-11/2 | 7:00 PM -6:00 AM |
| I-81 | Wilkes-Barre Township | Lane Restriction | Litter Pickup | 11/1-11/4 | 7:00 AM - 3:00 PM |
| I-81 | Jenkins Township | Lane Restriction | Litter Pickup | 10/31-11/4 | 7:00 AM - 3:00 PM |
| 309 Bridge over Susquehanna | Luzerne County | Lane Restriction | Bridge Inspection | 10/31-11/3 | 9:00 AM - 3:30 PM |
| 309 | Dallas Township | Lane Restriction | Crack Sealing | 10/31-11/4 | 7:00 AM - 3:00 PM |
| 1026 | Dallas Township | Lane Restriction | Crack Sealing | 10/31 | 7:00 AM - 3:00 PM |
| 1030 | Lake Township | Lane Restriction | Crack Sealing | 10/31-11/1 | 7:00 AM - 3:00 PM |
| 1047 | Dallas Township | Lane Restriction | Crack Sealing | 11/1-11/3 | 7:00 AM - 3:00 PM |
| 1063 | Harveys Lake Borough | Lane Restriction | Crack Sealing | 11/4 | 7:00 AM - 3:00 PM |
| 1065 | Lake Township | Lane Restriction | Crack Sealing | 11/2-11/4 | 7:00 AM - 3:00 PM |
| 3006 | Slocum Township | Lane Restriction | Crack Sealing | 10/31-11/2 | 7:00 AM - 3:00 PM |
| Various | Luzerne County | Lane Restriction | Sign Repairs | 10/31-11/4 | 7:00 AM - 3:00 PM |
| | | | | | |
| Pike County | |||||
| State Route/Exit | Township | Closure/Restriction | Work | Dates | Time |
| 434 | Shohola Township | Lane Restriction | Crack Sealing | 10/31-11/4 | 7:00 AM - 3:00 PM |
| 739 | Delaware Township | Lane Restriction | Shoulder Skin Patching | 10/31 | 7:00 AM - 3:00 PM |
| 1003 | Lackawaxen Township | Lane Restriction | Bridge Repairs | 10/31-11/2 | 7:00 AM - 3:00 PM |
| 1009 | Blooming Grove Township | Lane Restriction | Trench Restoration | 11/1-11/2 | 7:00 AM - 3:00 PM |
| 1014 | Lackawaxen Township | Lane Restriction | Shoulder Stability | 10/31-11/4 | 7:00 AM - 3:00 PM |
| 1017 | Westfall Township | Lane Restriction | Trench Restoration | 11/3-11/4 | 7:00 AM - 3:00 PM |
| 2001 | Delaware Township | Lane Restriction | Deck Patching | 11/3 | 7:00 AM - 3:00 PM |
| 2004 | Dingman Township | Lane Restriction | Deck Patching | 11/4 | 7:00 AM - 3:00 PM |
| 2009 | Dingman Township | Lane Restriction | Deck Patching | 11/4 | 7:00 AM - 3:00 PM |
| Various | Pike County | Lane Restriction | Sign Review | 10/31 | 7:00 AM - 3:00 PM |
| | | | | | |
| Susquehanna County | |||||
| State Route/Exit | Township | Closure/Restriction | Work | Dates | Time |
| I-81 | Lenox Township | Lane Restriction | Patching and Cutting | 10/31-11/3 | 7:00 AM - 3:00 PM |
| I-81 | Great Bend Township | Lane Restriction | Bridge Repairs | 10/31-11/4 | 7:00 AM - 3:00 PM |
| I-81 | Lenox Township | Lane Restriction | Bridge Repairs | 10/31-11/4 | 7:00 AM - 3:00 PM |
| 374 | Lenox Township | Lane Restriction | Crack Sealing | 11/4 | 7:00 AM - 3:00 PM |
| 1004 | Thompson Township | Lane Restriction | Base Repair | 10/31 | 7:00 AM - 3:00 PM |
| 1019 | Jackson Township | Lane Restriction | Paving | 11/1-11/4 | 7:00 AM - 3:00 PM |
| 1019 | Lenox Township | Lane Restriction | Patch and Cutting | 10/31-11/4 | 7:00 AM - 3:00 PM |
| 1019 | Ararat Township | Lane Restriction | Paving | 10/31 | 7:00 AM - 3:00 PM |
| 2046 | Ararat Township | Lane Restriction | Crack Sealing | 11/4 | 7:00 AM - 3:00 PM |
| 2096 | Lathrop Township | Lane Restriction | Trench Restoration | 11/1-11/2 | 7:00 AM - 3:00 PM |
| 3009 | Auburn Township | Lane Restriction | Crack Sealing | 10/31-11/4 | 7:00 AM - 3:00 PM |
| 3009 | Auburn Township | Lane Restriction | Pipe Replacement | 11/3 | 7:00 AM - 3:00 PM |
| 3023 | Lathrop Township | Lane Restriction | Pipe Replacement | 10/31 | 7:00 AM - 3:00 PM |
| 3029 | Forest Lake Township | Lane Restriction | Pipe Replacement | 11/4 | 7:00 AM - 3:00 PM |
| | | | | | |
| Wayne County | |||||
| State Route/Exit | Township | Closure/Restriction | Work | Dates | Time |
| 191 | Buckingham Township | Lane Restriction | Patching | 10/31-11/4 | 7:00 AM - 3:00 PM |
| 191 | Lehigh Township | Lane Restriction | Shoulder Cutting | 11/1 | 7:00 AM - 3:00 PM |
| 507 | Lehigh Township | Lane Restriction | Crack Sealing | 10/31-11/4 | 7:00 AM - 3:00 PM |
| 3030 | Waymart Borough | Lane Restriction | Crack Sealing | 10/31 | 7:00 AM - 3:00 PM |
| 3044 | Lehigh Township | Lane Restriction | Shoulder Cutting | 10/31 | 7:00 AM - 3:00 PM |
| | | | | | |
| Wyoming County | |||||
| State Route/Exit | Township | Closure/Restriction | Work | Dates | Time |
| 6 |
Tunkhannock Township | Lane Restriction | Crack Sealing | 11/2-11/4 | 7:00 AM - 3:00 PM |
| 1017 | Factoryville Borough | Lane Restriction | Trench Restoration | 11/1 | 7:00 AM - 3:00 PM |
| 2013 | Falls Township | Lane Restriction | Trench Restoration | 10/31 | 7:00 AM - 3:00 PM |
| 3002 | Noxen Township | Lane Restriction | Bridge Repairs | 10/31-11/4 | 7:00 AM - 3:00 PM |
| 3004 | Mehoopany Township | Lane Restriction | Paving | 10/31-11/4 | 7:00 AM - 3:00 PM |
Long Term Projects
| State Route | Exit/Mile Marker | County(ies) | Township | Closure/Restriction | Work | Dates | Time |
| N/A | Lackawanna | Clifton Township | Closed | A Lackawanna County-owned bridge is closed indefinitely on Keystone Rd. in Clifton Township off State Route 435. The road has no outlet. | Indefinitely | ||
| SR 307 | Lackawanna | Roaring Brook Township | Lane Restriction | This project involves the full replacement of a culvert that crosses under a four-lane road, State Route 307 (Scranton Pocono Highway) over Green Run in Roaring Brook Township, Lackawanna County. | Nov. 2022 | ||
| SR 6 Casey Highway | Lackawanna | Lane Restriction | The concrete pavement and bridge preservation project on Route 6 (Casey Highway) is ongoing. This project addresses the aging concrete roadway pavement by replacing damaged and broken slabs where necessary, while retrofitting existing slabs to give them stability and cleaning and sealing all pavement joints. Preservation work is performed on the highway to preserve the existing concrete pavement. This type of project is a cost-effective means of extending the service life of a concrete roadway. Pavements left to deteriorate without timely preservation treatments are more likely to require costly and disruptive major rehabilitation or reconstruction projects. After all the concrete repairs are complete, a procedure called diamond grinding will be performed by the contractor. Diamond grinding will correct surface imperfections and improve ride quality on the Casey Highway. The project began in April of 2022 and be completed in 2024. A similar project was just completed 2-years ago at the I-81 and I-84 Interchange in Dunmore. |
2024 | |||
| I-84 EB/WB | Lackawanna | Roaring Brook Township | Lane Restriction | This project consists of milling and resurfacing existing bituminous interstate roadways and ramps. Other work includes guide rail, base, joint, temporary traffic control, and pavement markings. | Nov. 2023 | ||
| SR 107 | Lackawanna | Scott Township | Lane Restriction | The project consists of improvements to SR 107, section 251 in Lackawanna County. The project includes a bridge rehabilitation on SR 107 (Heart Lake Road) between Interstate 81 and SR 1013 (Tompkinsville Road/Bell Mountain) in Scott Township, Lackawanna County. There is a lane restriction with traffic lights to control traffic. | TBD | 7:00 AM - 5:00 PM | |
| SR 307 | Lackawanna | Roaring Brook Township | Right Lane Closure | The right lane is closed northbound on SR 307. Stone arch over Williams Creek end wall and parapet issues. | TBD | ||
| SR 307 | Lackawanna | Spring Brook Township | Right Lane Restriction | The right lane shoulder is closed on SR 307 due to a slide issue. | TBD | ||
| I-380 | Lackawanna | Lane Restriction | The district-wide guide rail project will be installing guide rail at I-380 NB and SB from mile marker 23 to mile marker 13. | Nov. 2022 | 7:00 AM - 5:00 | ||
| I-84 EB/WB | Lackawanna/Wayne | Lane Restriction | This project consists of milling and resurfacing existing bituminous interstate roadways and ramps. Other work includes guide rail, base, joint, temporary traffic control, and pavement markings. The contractor will have the right lane closed eastbound between MM 16.1 to 18.5 & westbound between MM 18.5 to 17.5 for paving. Contractor will also be paving the on and off ramps at exit 17 in the eastbound lane. The contractor will also be working on the substructure of the bridge at MM 13 westbound. | Nov. 2022 | 6:30 AM-5:00 PM | ||
| I-84 | Lackawanna/Wayne | Single Lane Closure | Temporary bridge deck repair work, installation of I-84 EB bridge girders, floor beams, deck pans, overhang jacks, reinforcing steel, place deck and parapet concrete, construct I-84 EB bridge approach slabs, install drainage basins, form, and pour WB pier #2/pier #2 plinth. Construct I-84 EB Phase 2/2A median side pavement in preparation for stage 3 mainline traffic switch and perform railroad bridge steel repairs. The I-84 over Lackawanna Railroad/Roaring Brook and SR 435 Section 282 project includes the replacement of three bridge structures and associated roadway work on I-84 and SR 435. This is the Twin Bridge Project. | TBD | 7:00 AM - 5:00 PM | ||
| SR 4005 | Lackawanna | Benton Township | Closed | The project consists of reconstruction and improvements of a certain section of SR 4005 Section 270 in Benton Township, Lackawanna County. The project scope of work consists of a bridge rehabilitation/superstructure replacement over the Norfolk Southern Railroad. A detour will be used to maintain traffic during the project | Nov. 2022 | 7:00 AM to 5:00 PM | |
| SR 8015 | Lackawanna | Clarks Summit | Shoulder Restriction | This work consists of the structure rehabilitation of two state-owned culverts on SR 8015 Section D51. The shoulder will be closed all summer. | Nov. 2022 | ||
| I-80/I-81 | Luzerne | Lane Restriction | Concrete pavement preservation project on I-80 and I-81 in Luzerne County. The project will cover several miles on I-80 and I-81. The project will address distressed concrete roadway pavement by replacing damaged and broken slabs where necessary and diamond grinding for ride quality. The lane closures will be temporary starting at the Luzerne /Columbia County line and working towards SR 93 interchange. The contractor will be working Monday through Thursday into November 2022 doing concrete roadway patches. All lanes will be open at the end of each workday and on weekends. |
Nov. 2022 | 7:00 PM - 6:00 AM | ||
| I-81/115/309 | Luzerne | Lane Restriction | For the rehabilitation and improvement of a certain section of state highways in Luzerne County, in various municipalities. Bridges are on I-81, SR 115, and SR 309 Cross Valley. Work will continue throughout the winter. | TBD | 7:00 AM to 5:00 PM | ||
| SR 309/11/92 | Luzerne | Lane Restriction | Resurfacing contract for 17 miles of roadway on Route 309 (North Cross Valley Expressway), Route 11 (Wyoming Avenue), Route 92 (Exeter Avenue), Route 2045 (South Main Road), and ADA ramp construction on Route 1009 (Market Street), Luzerne County. The project started the week of 8/2/21 and the contractor is working on SR 2045 (South Main Street). | TBD | 7:00 AM - 5:00 PM | ||
| SR 3007 | Luzerne | Slocum Township | Closed | State Route 3007 (Blue Ridge Trail) is closed from SR 2042 (Stairville Rd) to SR 3008 (Slocum Rd) in Slocum Township, Luzerne County for a culvert replacement. A detour is in place. | Oct. 2022 | 7:00 AM - 5:00 PM | |
| SR 390 | Pike | Palmyra Township | Lane Restriction | The project includes replacing the bridge on SR 390 around Fairview Lake. Traffic will be reduced to one lane with traffic lights installed. | May 2023 | 7:00 AM -5:00 PM | |
| SR 1012 | Pike | Lackawaxen Township | Shoulder Restriction | The shoulder was washed-out, and the pavement edge failed. The work is in the design stage. | TBD | ||
| SR 2002 | Pike | Dingman Township | Closed | This is a slope failure reconstruction project along SR 2002 (Wilson Hill Road), which is in the Delaware Water Gap Recreation Area. The proposed work includes the installation of a retaining wall, roadway reconstruction in the eastbound lane, minor roadway work in the opposite lane, guide rail, drainage, and pavement markings. A detour is in place. | Nov. 2022 | 7:00 AM -5:00 PM | |
| I-84 | Mile Marker 17-26 | Pike/Wayne | Green, Palmyra, Sterling | Single Lane Closure | The project consists of the reconstruction of Interstate I-84. The project length is approx. 8 miles. I-84 will be under a long-term restriction from mile marker 17 to 26, EB and WB. Westbound traffic will cross over in a single-lane pattern onto the Eastbound lanes. Traffic will be single lane from mile marker 21.5 to 26.0. There will be long-term single-lane closures on I-84 EB and WB between Exits 20 (Greentown / Wallenpaupack) and 26 (Promised Land/Tafton) (mile markers 21.5 to 26). The interstate will be down to single-lane traffic in each direction on the EB lanes while we close and reconstruct the WB lanes. The westbound rest area on Interstate 84 will be closed for the season. This will be located around mile marker 25.7. Traffic is currently bi-directional on the eastbound lanes separated by concrete barriers from mile markers 21.7 to 26. Westbound lanes are closed for reconstruction for 4 miles of roadway, one bridge structure over Shinny Mountain Road, and the on and off ramps for the westbound rest area. This will remain until the end of November 2022. |
2022 - 2023 | 7:00 AM - 5:00 PM |
| I-84 EB/WB | Mile Marker 43-46 | Pike | Lane Closure | Shoulder upgrades/crossover construction on I-84 from mile marker 43 to mile marker 46. There will be temporary single-lane closures on both east and westbound. There is a permanent lane closure 24/7. | Nov. 2022 | 7:00 AM - 5:00 PM | |
| SR 171 | Susquehanna | Oakland Borough | Lane Restrictions | The project will construct a retaining wall to repair a slope failure. Traffic will be maintained utilizing half-width construction with temporary signals. | Nov. 2022 | 7:00 AM - 5:00 PM | |
| SR 3029 | Susquehanna | Jessup Township | Lane Restriction | The project consists of a full concrete bridge replacement over the East Branch of the Wyalusing Creek on SR 3029 in Jessup Township. The work includes a closed lane of traffic with temporary signals. | Oct. 2022 | 7:00 AM - 5:00 PM | |
| SR 706 | Susquehanna | Rush Township | Lane Restrictions with Temporary Traffic Signals | SR 706 section 501 in Rush Township there will be single-lane restrictions with temporary traffic signals. The work involves complete demolition and new half-width construction of three structures. Three bridges under construction will be at the nearest intersection of SR 706 and Gage Road, SR 706 and Bomboy Road, and SR 706 and Devine Road. All 3 sites will have widened roadways, shoulders, new paved approaches, guide rail, and road markings when completed. | Nov. 2022 | 7:00 AM - 5:00 PM | |
| SR 3029 | Susquehanna | Lane Restriction | There will be a lane restriction on SR 3029 for mechanical edging and patching work. | Nov. 2022 | 7:00 AM-7:00 PM | ||
| SR 3029 | Susquehanna | Fairdale | Closed | Construction of box culvert beginning on Monday, October 3 on SR 3029 in Susquehanna County. The project is about 1 mile north of SR 706 in Fairdale. This project requires SR 3029 to be closed. A signed detour will be in place. | Nov. 2022 | 7:00 AM - 5:00 PM | |
| SR 1006 | Wayne | Damascus/Berlin Township | Closed | SR 1006 (Peggy Runway Road) is closed. The area affected is between the intersection of SR 652 & SR 1006 at Segment 0060/2808 in Damascus Twp. to the intersection of SR 1006 and Cortez Road Segment 0050/2074 in Berlin Twp. | Nov. 2022 | ||
| SR 1002 | Wayne | Milanville | Closed | Skinners Falls bridge is closed until further notice. A PEL Study is being completed. | TBD | N/A | |
| SR 92 | Wyoming | Falls Township | Lane Restriction | There will be stone arch culvert rehabilitation on State Route 92, Section 750, over a tributary to the Susquehanna River, in Falls Township, Wyoming County. The contractor will restabilize the existing floor by encapsulating the timbers in concrete and reconstructing the existing upstream headwall and wing walls. The structure is shared between the state and the railroad company, only the state's half will be included in the project. There will be one lane work zone with a width restriction for the improvement. It will be controlled by temporary traffic signals and concrete barriers. Stage two traffic control is now in place. | Nov. 2022 | ||
| SR 11, SR 858, SR 1031, and SR 87 | Susquehanna and Wyoming Counties | Lane Restriction | This project is for the resurfacing of approximately 13.9 miles of existing roadway on the following state routes in Susquehanna and Wyoming Counties. SR 11, SR 858, SR 1031, and SR 87. | TBD | |||
| SR 2008, SR 2013, SR 2015, SR 2017, SR 2021, SR 2025 | Wyoming | Falls Township | Lane Restriction | Kriger Construction will be performing mechedge paving and patching work. The work will be on SR 2008, SR 2013, SR 2015, SR 2017, SR 2021, and SR 2025. The work will be mostly in the Falls PA area. There will be a single-lane closure while the work is being performed. | Nov. 2022 | 7:00 AM-5:00 PM | |
| SR 2013 | Wyoming | Falls Township | Lane Restriction | The contractor will be repairing the bad areas on SR 2013 (Falls Road) in Wyoming County. The repair work will take place between Church Hill Road and the Lackawanna County Line. The section of Falls Road between the Buttermilk Falls Bridge and Church Hill Road will be milled and paved in the near future. | Nov. 2022 | 7:00 AM-5:00 PM |
Motorists can check conditions on major roadway miles by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information, and access to more than 1,000 traffic cameras.
511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1, or by following regional Twitter alerts accessible on the 511PA website.
Subscribe to PennDOT news and traffic alerts in Lackawanna, Luzerne, Pike, Susquehanna, Wayne, and Wyoming counties at www.penndot.gov/District4.
Information about infrastructure in District 4, including completed work and significant projects, is available at www.penndot.gov/D4Results.
Follow local PennDOT news on Twitter and like the department on Facebook and Instagram.
MEDIA CONTACT: Michael Taluto, (570) 963-3502
# # #
Legal Disclaimer:
EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.