FHWA Finalizes Rule on the Construction Manager/General Contractor Contracting Method

U.S. Department of Transportation, Office of Public Affairs, 1200 New Jersey Avenue, SE, Washington, D.C. 20590, www.dot.gov/briefingroom - News Follow us on Twitter @USDOTFHWA USDOT briefing room

DOT 149-16 Friday, December 2, 2016 Contact: Nancy Singer Tel.: (202) 366-0660

FHWA issued a final rule this week that allows the Construction Manager/General Contractor (CM/GC) method to be used on highway federal-aid projects nationwide. Under this contracting method, a single contractor may provide pre-construction and construction services. CM/GC allows construction expertise to be used during the design phase, often leading to innovation, improved quality and reduced time and cost on complex projects. The final rule was required under MAP-21 and effectively opens the door for the use of the CM/GC method by state departments of transportation. The final rule formalizes FHWA’s procedures for approving and authorizing CM/GC projects. CM/GC is part of the agency’s Every Day Counts initiative designed to foster innovation and accelerate project delivery.

# # #

Legal Disclaimer:

EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.