There were 1,898 press releases posted in the last 24 hours and 483,979 in the last 365 days.

Walton County Public Works’ Projects in Progress report

Walton County Projects in Progress

 

Walton County, FL, 08/03/26 - Walton County Public Works in-house crews have been hard at work on improving the community’s infrastructure. Below is a list of highlights from these important efforts. 

 

ORANGE BLOSSOM AVENUE (EAST AND WEST) DIRT TO PAVE

Project Improvements:

•        Paving 0.26 miles extending from Brookside Drive to the end of maintenance

•        Pavement striping

Current Status:

•        Construction (stabilizing road base)

•        Drainage completed

•        Sod installation 

Traffic Impacts:

Intermittent shoulder and lane closures are anticipated throughout the duration of the project.

 

POINSETTA AVENUE (EAST AND WEST) DIRT TO PAVE

Project Improvements:

•        Paving 0.32 miles extending from Walden Road to the end of maintenance

•        Pavement striping

•        Sod installation

Current Status:

•        Construction (stabilizing road base) 

•        Drainage Improvements-drainage inlets installed

Traffic Impacts:

Intermittent shoulder and lane closures are anticipated throughout the duration of the project.

13th STREET DIRT-TO-PAVE AND DRAINAGE IMPROVEMENTS

Project Improvements:

•        Paving 0.64 miles extending from Churchill Bayou Road to the end of maintenance

•        Pavement Striping

Current Status: 

•        Under Construction (stabilization) 

•        Drainage Improvements ongoing

Traffic Impacts: Intermittent shoulder and lane closures are anticipated throughout the duration of the project.

 

FORMBY STREET OVERLAY

Project Improvements:

•        The overlay operation will commence on Formby Street extending from the intersection of Mossy Oak Lane and will proceed for approximately 0.2 miles.

Current Status: 

•        Base is prepped and ready to overlay

Traffic Impacts: Intermittent shoulder and lane closures are anticipated throughout the duration of the project.

 

BAY GROVE ROAD AND ROLLIN BLVD DRAINAGE IMPROVEMENT

Project Improvements:

•        The installation of a drainage pipe at the intersection of Bay Grove Road and Rollin Boulevard.

Current Status: 

•        COMPLETED

Traffic Impacts: Intermittent shoulder and lane closures are anticipated throughout the duration of the project

 

ADDITIONAL PROJECTS

•        Lake Drive- Working on the multi-use path, repairing culvert headwalls and ditch maintenance

•        W Harborview Road-Construction of a new sidewalk 

•        Paxton Senior Center- Asphalt paving parking lot and striping

•        Eagle Springs Golf Course-Construction of new parking lot

•        Satsuma Road (Choctaw Beach)- Installation of drainage pipe

•        Mossy Head Community Center/Beaver Dam Park-striping parking lot

•        TDC property-demolition of old mobile home that was left on the property

Legal Disclaimer:

EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.