Sum Certain Must Be Included in Claim, Not in Later Discovery

What happens if you submit a claim to a contracting officer (“CO”) but instead of including a “sum certain” as required by the Contract Disputes Act (“CDA”) you state you will furnish that sum during discovery?  The simple answer is that your claim is likely to be dismissed at some early stage of the litigation. See Canpro Investments, Ltd. v United States, No. 16-268C (Fed. Cl. May 4, 2023). 

In order to comply with CDA requirements, a claim must:

  1. Be in writing
  2. Request a final decision from the contracting officer
  3. Seek payment “as a matter of right”
  4. Seek a sum certain (an exact amount)
  5. Be made with specificity
  6. Be certified if over $100,000
  7. Be submitted to the contracting officer
  8. Be nonroutine (or in dispute), i.e. not be an invoice, voucher or other routine request for payment that was not in dispute when submitted.

Canpro had a lease with the General Services Administration and filed a CDA claim for damages relating to overcrowding of the premises (a Social Security Branch office), and because some visitors engaged in behavior inappropriate for commercial space.  Instead of including a sum certain for its claim and damages, Canpro “reserved the right to amend its claim for damages as the litigation progresses.” 

Canpro submitted a second CDA claim referring to “millions of dollars in damages” caused by excess volume of occupants, loss of reputation and loss of revenue.  Finally, in its Seventh Amended Initial Disclosures ordered by the court, Canpro asserted damages “in a range of $36,332,000 to $41,332,000.”  None of these categories of damages satisfies the CDA “sum certain” requirements.  Further, Canpro relied especially on the future opinions of litigation experts.

In dismissing the CDA claim, the court noted that Canpro had things backwards.  The “point of the CDA presentment requirement is not for contractors to check a box before expert discovery; it is to give the contracting officer notice and opportunity to pay a ‘sum certain’”.  There is no jurisdiction at the Court of Federal Claims without these mandated requirements being met, and there will be no litigation and no expert discovery.  Canpro tried to save for liltigation something that should have been presented to the contracting officer.  Canpro’s CDA claim was dismissed by the court because it had no jurisdiction over this dispute as presented by Canpro.

Takeaway.  Always ensure to include all the necessary elements of the claim when you submit it to your CO.  If you do not state a “sum certain” then the amount must be readily ascertainable from the existing documents (e.g. if you claim a right to payment of a $50,000 invoice (denied by the agency) and include the invoice with your claim, your sum certain is readily ascertainable.)

For other helpful suggestions on government contracting, visit:

Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes.

Legal Disclaimer:

EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.