There were 125 press releases posted in the last 24 hours and 463,033 in the last 365 days.

Continental Gold Announces a Positive Feasibility Study for the Buritica Project


/EINPresswire.com/ -- TORONTO, ON--(Marketwired - February 24, 2016) -  Continental Gold Inc. (TSX: CNL)   (OTCQX: CGOOF) ("Continental" or the "Company") is pleased to announce the results of an independent Feasibility Study ("FS"), prepared in accordance with National Instrument 43-101 ("NI 43-101"), for its 100%-owned Buriticá project in Antioquia, Colombia. The FS was authored by JDS Energy and Mining Inc. ("JDS"), and M3 Engineering & Technology Corp. was responsible for designing the processing facilities and related surface infrastructure. The FS indicates that the Buriticá project will be host to an economically robust, high-grade underground gold mine. All dollar amounts are quoted in U.S. Dollars; all cash cost information is net of silver by-product credits.

Feasibility Study Highlights

  • Maiden mineral reserve for the combined Yaraguá and Veta Sur vein systems totaling 3.7 million ounces of gold and 10.7 million ounces of silver (13.7 million tonnes grading 8.4 g/t gold and 24.3 g/t silver);
  • Gold and silver recoveries of 94.1% and 59.9%, respectively, over the life of the mine ("LOM");
  • A 14-year mine life that will produce 3,492,000 ounces of recovered gold and 6,425,000 ounces of recovered silver;
  • The first five years of production will average approximately 282,000 ounces of gold and 494,000 ounces of silver annually, at a total average cash cost of $387 per ounce of gold (including silver credits). LOM production will average 253,000 ounces of gold and 466,000 ounces of silver annually, at a total cash cost of $411 per ounce of gold (including silver credits), placing Buriticá in the lowest cash-cost quartile globally;
  • Estimated project capital cost, including contingency, of $389.2 million;
  • LOM average operating costs of $111.59 per tonne milled (including royalty, doré transport and refining charges);
  • Base case scenario utilizes a gold price of $1,200/ounce, a silver price of $15/ounce and an exchange rate (US$:COP (Colombian Peso)) of 2,850, resulting in the following economics:
    • The after-tax net present value at a 5% discount ("NPV5") amounts to $0.86 billion;
    • Internal Rate of Return ("IRR") of 31.2%; and
    • Capital payback of 2.3 years;
  • High case scenario utilizing a gold price of $1,400/ounce, a silver price of $17/ounce and an exchange rate (US$: COP) of 2,850, resulting in the following economics:
    • The after-tax NPV5 amounts to $1.16 billion;
    • IRR of 37.8%; and
    • Capital payback of 1.8 years.

Tables 1 and 2 show economic results with varying metal prices and the economic model basis:

Table 1: Summary of Buriticá Project Economics by Precious Metal Price

                                                                            
----------------------------------------------------------------------------
Gold Price ($/oz)               $1,000   $1,100   $1,200   $1,300   $1,400  
----------------------------------------------------------------------------
Silver Price ($/oz)               $12      $13      $15      $16      $17   
----------------------------------------------------------------------------
After-Tax Net Cash Flow                                                     
 ($billion)                      $0.99    $1.22    $1.44    $1.67    $1.89  
----------------------------------------------------------------------------
After-Tax NPV5 ($billion)(1)     $0.56    $0.71    $0.86    $1.01    $1.16  
----------------------------------------------------------------------------
After-Tax IRR                    23.6%    27.5%    31.2%    34.6%    37.8%  
----------------------------------------------------------------------------
Payback Period (years)            3.0      2.6      2.3      2.0      1.8   
----------------------------------------------------------------------------
Exchange Rate (US$: COP)         2,850    2,850    2,850    2,850    2,850  
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
Years 1-5 Average Total Cash                                                
 Cost ($/payable oz)(2)           $384     $386    $387      $389     $392  
----------------------------------------------------------------------------
Years 1-5 Average All-in                                                    
 Sustaining Cash Cost                                                       
 ($/payable oz)(2)                $492     $495    $496      $498     $501  
----------------------------------------------------------------------------
Years 1-5 Average After-Tax                                                 
 Annual Cash Flow ($million)      $127     $145    $163      $181     $199  
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
LOM Average Total Cash Cost                                                 
 ($/payable oz)(2)                $408     $410    $411      $414     $416  
----------------------------------------------------------------------------
LOM All-in Sustaining Cash Cost                                             
 ($/payable oz)(2)                $489     $492    $492      $495     $497  
----------------------------------------------------------------------------
LOM Average After-Tax Annual                                                
 Cash Flow ($million)(3)          $100     $116    $133      $149     $165  
----------------------------------------------------------------------------
                                                                            

(1) NPV is discounted to September 1, 2016.

(2) Cash Costs include silver credits.

(3) Average LOM cash flow calculated on 13.8-year production period.

"The Feasibility Study confirms that the Buriticá project offers immediate development potential and would be among one of the lowest cost precious metal mines in the world. The construction phase of the mine would employ over 1,200 people at peak activity (approximately 900 during operations), and would be the largest single gold mine in Colombia once production commences," stated Ari Sussman, Chief Executive Officer of Continental. "With support from our employees, the Buriticá community and local, departmental and national governments of Colombia, we look forward to building Latin America's next great high-grade gold mine. Initial production is scheduled to commence from the mineral reserves of only two deposits. With existing large Inferred mineral resources already in place and mineralization open in most directions, not only do these deposits offer significant future growth, but exploration has outlined four other large vein system targets within five kilometres that are drill ready."

"The Feasibility Study results are compelling and present an opportunity to build a large, safe and modern mine using conventional technology," remarked Donald Gray, Chief Operating Officer. "Not only do the results confirm our expectations, but they also increase our confidence in assertively moving forward with the Buriticá project."

Table 2: Feasibility Study Basis

                                                                            
----------------------------------------------------------------------------
Gold Price                                       $1,200 per ounce           
----------------------------------------------------------------------------
Silver Price                                     $15 per ounce              
----------------------------------------------------------------------------
Total Resource Tonnes to be Mined                13,717,000                 
----------------------------------------------------------------------------
                                                 2,100, increasing to 3,000 
Processing Rate (tonnes per day)                 by third year              
----------------------------------------------------------------------------
Mine Life                                        14 years                   
----------------------------------------------------------------------------
Planned Dilution(1)                              36%                        
----------------------------------------------------------------------------
Minimum Mining Width                             1.0 metres                 
----------------------------------------------------------------------------
                                                 1.9 metres (Yaraguá) 3.2   
Average Mining Width                             metres (Veta Sur)          
----------------------------------------------------------------------------
Gold Grade                                       8.4 g/t                    
----------------------------------------------------------------------------
Silver Grade                                     24.3 g/t                   
----------------------------------------------------------------------------
Gold Recovery Rate                               94.1%                      
----------------------------------------------------------------------------
Silver Recovery Rate                             59.9%                      
----------------------------------------------------------------------------
Total Gold Ounces Recovered                      3,492,000                  
----------------------------------------------------------------------------
Total Silver Ounces Recovered                    6,425,000                  
----------------------------------------------------------------------------
Initial Project CAPEX                            $389.2 million             
----------------------------------------------------------------------------
Contingency (included within Initial Project                                
CAPEX)                                           $35.4 million              
----------------------------------------------------------------------------
LOM Sustaining Capital Costs                     $272.5 million             
----------------------------------------------------------------------------
Mining Costs                                     $57.21/tonne               
----------------------------------------------------------------------------
Processing Costs including Tailing Storage                                  
Facility                                         $26.16/tonne               
----------------------------------------------------------------------------
G&A                                              $17.13/tonne               
----------------------------------------------------------------------------
                                                 4.0 g/t Au (Veta Sur) 3.8  
Cut-Off Grade                                    g/t Au (Yaraguá)           
----------------------------------------------------------------------------
Royalty                                          3.20%                      
----------------------------------------------------------------------------
Effective Tax Rate                               33.0%                      
----------------------------------------------------------------------------
                                                                            

(1) Dilution calculated as below cut-off grade tonnes divided by total tonnes mined.

Details

Buriticá Mineral Reserves

Mineral Reserves from the FS for the Buriticá project are derived from the Mineral Resource Estimate for the Yaraguá and Veta Sur vein systems set out in the technical report entitled "Independent Technical Report and Resource Estimate on the Buriticá Gold Project 2015" (the "2015 Technical Report") dated August 7, 2015, with an effective date of May 11, 2015, led by independent consultants Mining Associates Limited. The Mineral Reserves are based on 271,003 metres of drill core sampling and 7,215 metres of underground sampling (as at May 11, 2015).

Mineral Reserve estimates by deposit and category are summarized in Tables 3, 4 and 5.

Table 3: Yaraguá Mineral Reserve Estimate

                                                                            
----------------------------------------------------------------------------
          RESERVE                    GRADES              CONTAINED METAL    
----------------------------------------------------------------------------
   Category       Tonnes    Gold (g/t)  Silver (g/t)  Gold (oz)  Silver (oz)
----------------------------------------------------------------------------
    Proven        450,600       20.5        47.6       297,000     690,000  
----------------------------------------------------------------------------
   Probable      8,378,800      7.0         20.8      1,889,000   5,609,000 
----------------------------------------------------------------------------
   Total P&P     8,829,400      7.7         22.2      2,186,000   6,299,000 
----------------------------------------------------------------------------
Notes: Based on a 3.8 g/t cut-off grade, $950 per ounce gold price, and     
US$:COP exchange rate of 2,850. Rounding of some figures may lead to minor  
discrepancies in totals.                                                    
----------------------------------------------------------------------------
                                                                            

Table 4: Veta Sur Mineral Reserve Estimate

                                                                            
----------------------------------------------------------------------------
            RESERVE                     GRADES            CONTAINED METAL   
----------------------------------------------------------------------------
      Category        Tonnes   Gold (g/t) Silver (g/t) Gold (oz) Silver (oz)
----------------------------------------------------------------------------
       Proven         226,800      22.2       84.7      162,000    617,000  
----------------------------------------------------------------------------
      Probable       4,660,600     9.1        25.4     1,362,000  3,803,000 
----------------------------------------------------------------------------
     Total P&P       4,887,400     9.7        28.1     1,524,000  4,420,000 
----------------------------------------------------------------------------
Notes: Based on a 4.0 g/t cut-off grade, $950 per ounce gold price, and     
US$:COP exchange rate of 2,850. Rounding of some figures may lead to minor  
discrepancies in totals.                                                    
----------------------------------------------------------------------------
                                                                            

Table 5: Combined Yaraguá and Veta Sur Mineral Reserve Estimate

                                                                            
----------------------------------------------------------------------------
            RESERVE                     GRADES            CONTAINED METAL   
----------------------------------------------------------------------------
      Category        Tonnes   Gold (g/t) Silver (g/t) Gold (oz) Silver (oz)
----------------------------------------------------------------------------
       Proven         677,400      21.1       60.0      459,000   1,307,000 
----------------------------------------------------------------------------
      Probable       13,039,400    7.8        22.5     3,251,000  9,412,000 
----------------------------------------------------------------------------
     Total P&P       13,716,800    8.4        24.3     3,710,000 10,719,000 
----------------------------------------------------------------------------
Notes: Based on cut-off grades of 3.8 g/t for Yaraguá and 4.0 g/t for Veta  
Sur, $950 per ounce gold price, and US$:COP exchange rate of 2,850. Rounding
of some figures may lead to minor discrepancies in totals.                  
----------------------------------------------------------------------------
                                                                            

Mining and Processing

The FS is based on a multiple ramp access underground mining operation, whole ore cyanide leach processing facility, dry-stacked filtered tailing and related infrastructure capable of mining and processing 2,100 tonnes per day ("tpd"), ramping up to 3,000 tpd by year three. LOM production profile is summarized in Table 6.

The mine is designed to initially develop two high-grade zones to minimize pre-production development time and capital and maximize early revenues. Mining methods selected for the Buriticá project were chosen to maintain mining flexibility and selectivity for the various ground conditions anticipated. The majority of mineral reserves will be mined by long-hole open stoping (59% stoping plus 25% stope development) on 15-metre sublevels, and overhand cut-and-fill (15%) with average mining costs of $57.21/tonne over LOM. Some shrinkage stope extraction will be used for narrower, isolated veins. Paste backfill made from a mixture of tailing and cement will be the primary backfill material, with unconsolidated waste rock being used in the cut-and-fill stopes. An internal raise system will direct ore and waste to the Higabra tunnel (already constructed by the Company), the main haulage level which will daylight adjacent to the process plant.

The majority of the mineral reserves in the Yaraguá and Veta Sur systems are located above the elevation of the Higabra tunnel, providing an advantageous gravity scenario for ore and waste movement and de-watering. A total of 300,000 metres of primary and secondary development are contemplated over the 14-year mine life, with approximately 53,000 metres of definition drilling projected ahead of commercial production.

Ore will be processed using a conventional crushing-grinding-gravity-cyanidation circuit with doré sold to a third party smelter. Metallurgical test-work completed to date demonstrates average recovery rates of 94.1% for gold and 59.9% for silver on a blended basis from the Yaraguá and Veta Sur mineral reserves. Processing costs of $26.16/tonne have been established over LOM.

Filtered tailing and waste rock not used for backfill will be placed in a single tailing storage facility. The integrated design utilizes the waste rock for stability and erosion protection.

Table 6: LOM Production Profile

                                                                            
     -----------------------------------------------------------------------
        Resource     Resource     Gold     Silver                           
       Mined (kt)  Milled (kt)    (g/t)     (g/t)          Production       
                                                   -------------------------
                                                     Gold (kOz) Silver (kOz)
----------------------------------------------------------------------------
  PP       97           82         6.9      22.5         17          36     
----------------------------------------------------------------------------
  1       814          816        12.2      37.1        291          469    
----------------------------------------------------------------------------
  2       840          833        11.8      34.7        296          482    
----------------------------------------------------------------------------
  3      1,079        1,080        8.6      28.0        282          573    
----------------------------------------------------------------------------
  4      1,068        1,080        7.7      21.4        253          466    
----------------------------------------------------------------------------
  5      1,103        1,073        8.8      22.2        287          482    
----------------------------------------------------------------------------
  6      1,070        1,092        8.3      22.6        277          495    
----------------------------------------------------------------------------
  7      1,104        1,110        8.1      23.0        274          526    
----------------------------------------------------------------------------
  8      1,104        1,110        8.1      24.2        273          544    
----------------------------------------------------------------------------
  9      1,103        1,092        7.6      22.0        252          482    
----------------------------------------------------------------------------
  10      990          999         7.6      21.5        231          425    
----------------------------------------------------------------------------
  11     1,106        1,110        7.5      20.8        253          468    
----------------------------------------------------------------------------
  12     1,061        1,055        7.0      20.3        223          434    
----------------------------------------------------------------------------
  13      826          833         7.5      22.9        190          378    
----------------------------------------------------------------------------
  14      353          354         8.8      25.5         94          166    
----------------------------------------------------------------------------
TOTAL   13,717       13,717       8.4       24.3       3,492       6,425    
----------------------------------------------------------------------------
                                                                            

Notes: Reported figures have been rounded; minor variations may occur during the addition of rounded numbers; k=thousands.

Capital Costs

Capital costs for the Buriticá project were estimated under the assumption that any acquisition costs or expenditures by the Company prior to this FS are deemed "sunk" costs, and are therefore not included in the analysis, other than for their impact on taxes. Initial capital costs are summarized in Table 7.

Table 7: Pre-Production Capital Cost Estimate

                                                                            
----------------------------------------------------------------------------
Capital Costs                                                               
                                                                   $ million
----------------------------------------------------------------------------
Underground Development, Infrastructure and Mine Equipment              95.3
----------------------------------------------------------------------------
Process Plant and Tailings Facility                                    115.8
----------------------------------------------------------------------------
General Site Facilities and Equipment and Site Development              43.7
----------------------------------------------------------------------------
Water Treatment Plant                                                   12.6
----------------------------------------------------------------------------
Power                                                                    5.4
----------------------------------------------------------------------------
Access Road                                                             10.9
----------------------------------------------------------------------------
Subtotal                                                               283.7
----------------------------------------------------------------------------
VAT (including $14.9 million available as income tax credits)           19.5
----------------------------------------------------------------------------
Owners and Project Indirect Cost and EPCM                               86.0
----------------------------------------------------------------------------
Total (including Contingency of $35.4 million)                        389.2 
----------------------------------------------------------------------------
                                                                            

Sustaining capital costs over the balance of the mine-life total $272.5 million, predominantly attributable to continued underground development, equipment rebuilds and replacement, and the ramp-up from 2,100 tpd to 3,000 tpd in the third year of commercial production.

Operating Costs

Operating cost estimates were prepared by JDS in conjunction with the Continental senior management team. Operating costs, before by-product credits, are outlined in Table 8. All-in sustaining cash cost is shown in Table 9.

Table 8: LOM Unit Operating Cost Estimate

                                                                            
----------------------------------------------------------------------------
Operating Costs                                                      $/tonne
----------------------------------------------------------------------------
Mining                                                                 57.21
----------------------------------------------------------------------------
Processing                                                             26.16
----------------------------------------------------------------------------
G&A (including refining and transportation)                            18.22
----------------------------------------------------------------------------
Royalty                                                                10.00
----------------------------------------------------------------------------
Total Operating Costs                                                111.59 
----------------------------------------------------------------------------
                                                                            

Table 9: Total and LOM All-in Sustaining Cash Cost Estimate

                                                                            
----------------------------------------------------------------------------
                                                    Unit           Value    
----------------------------------------------------------------------------
Total Cash Costs(1)                                  $M           $1,435    
----------------------------------------------------------------------------
Closure, Reclamation & Remediation(2)                $M             10      
----------------------------------------------------------------------------
Sustaining Capital Expenditure                       $M             272     
----------------------------------------------------------------------------
All-In Sustaining Cash Costs                         $M           $1,717    
----------------------------------------------------------------------------
Gold Sales                                    000's payable oz     3,489    
----------------------------------------------------------------------------
LOM All-In Sustaining Cash Costs per Ounce      $/payable oz       $492     
----------------------------------------------------------------------------
Initial Capex                                        $M             389     
----------------------------------------------------------------------------
Total All-In Sustaining and Construction                                    
 Costs per Ounce                                $/payable oz       $604     
----------------------------------------------------------------------------
                                                                            

(1) Net of silver credits totalling $27.50 per Au ounce.

(2) Net of salvage ($7.4M).

Upside Feasibility Study Potential

The FS excludes from consideration all inferred resources (as defined in the May 11, 2015 mineral resource estimate for the Yaraguá and Veta Sur vein systems and set out in the 2015 Technical Report). The Company will initiate an infill drilling program once permitting and project financing are obtained with the aim of upgrading the inferred resources into higher confidence categories. Additionally, the 2015 Technical Report concludes both the Yaraguá and Veta Sur vein systems remain open for expansions along strike to the west and at depth.

Table 10: Inferred Mineral Resource Estimate

                                                                            
----------------------------------------------------------------------------
          Combined Yaraguá and Veta Sur Inferred Mineral Resources          
               above a 3 g/t gold cut-off, as at May 11, 2015               
----------------------------------------------------------------------------
        RESOURCE                  GRADES                     METAL          
----------------------------------------------------------------------------
                 Tonnes   Gold    Silver  Gold Eq   Gold    Silver  Gold Eq 
   Category       (M)    (g/)t    (g/t)    (g/t)   (Moz)    (Moz)    (Moz)  
----------------------------------------------------------------------------
   Inferred       15.6     9.0      29      9.5      4.5     14.7     4.8   
----------------------------------------------------------------------------
Notes: Reported tonnage and grade figures have been rounded from raw        
estimates to reflect the order of accuracy of the estimate. Minor variations
may occur during the addition of rounded numbers. There have been no        
assumptions made as to metal prices or recoveries in this mineral resource  
estimate other than in gold equivalents that are calculated for Gold Eq =   
Gold + Silver/60. M in Figures and Tables represents millions.              
----------------------------------------------------------------------------
                                                                            

In addition, the FS has been prepared using an exchange rate (US$: COP) of 2,850, which impacts all COP-denominated capital, sustaining and operating costs incurred. As at February 23, 2016, the US$:COP exchange rate was 3,313, representing an approximate 16% devaluation from the rate utilized in the FS.

Financing and Cash Resources

The Company is financed to continue development activities and complete project permitting in 2016. In order to finance construction of the mine, discussions are underway with project lending providers. Any major financing facilities that may be afforded to the Company will be contingent on the Company completing project permitting.

Technical Information

A technical report to support the FS will be prepared in accordance with NI 43-101 and filed on SEDAR within 45 days of this press release. For information with respect to the key assumptions, parameters and risks associated with the results of the FS for the Buriticá project, the mineral resource and reserve estimates included therein and other technical information with respect to those initiatives, please refer to the technical report to be made available at www.sedar.com.

The FS was prepared, under the direction of JDS, by leading independent industry consultants, all Qualified Persons (QP) under NI 43-101. Consultants and QPs contributing to the FS are listed in Table 11.

Table 11: Feasibility Study Contributors

                                                                            
----------------------------------------------------------------------------
Qualified                                                                   
Person,                                                                     
Designation     Company         Scope of Responsibility                     
----------------------------------------------------------------------------
Austin                                                                      
Hitchins,       JDS Energy &    Geologic setting and Mineralization, Deposit
P.Geo.          Mining Inc.     type, Exploration, Drilling                 
----------------------------------------------------------------------------
Andrew J Vigar,                                                             
FAusIMM, MSEG   Mining          Mineral Resource Estimate, Sample           
Ian Taylor,     Associates      preparation, Analysis and Security, Data    
MAusIMM, MAIG   Limited         Verification                                
----------------------------------------------------------------------------
Stacy                                                                       
Freudigmann,    JDS Energy &                                                
P.Eng.          Mining Inc.     Mineral Processing and Metallurgical testing
----------------------------------------------------------------------------
                M3 Engineering                                              
Laurie Tahija,  & Technology    Recovery Methods, Design of Process Plant   
MMSA-QP         Corp.           and related surface infrastructure          
----------------------------------------------------------------------------
                Robertson                                                   
Jack Caldwell,  GeoConsultants                                              
P.Eng.          Inc.            Tailing Storage Facility                    
----------------------------------------------------------------------------
                                Mineral Reserve Estimate, Mining Methods,   
Greg Blaylock,  JDS Energy &    Mine Design and Infrastructure, Mining      
P.E.            Mining Inc.     Capital and Operating costs                 
----------------------------------------------------------------------------
Mike Levy, P.E. SRK Consulting  Mine Geomechanics                           
----------------------------------------------------------------------------
Mike Creek,     JDS Energy &                                                
P.E.            Mining Inc.     Environmental Studies, Permitting           
----------------------------------------------------------------------------
David Stone,    Minefill                                                    
P.E.            Services Inc.   Pastefill Design                            
----------------------------------------------------------------------------
Lyle A. Davis,                                                              
P.E. Michael    Montgomery &                                                
Rosko, P.G.     Associates Inc. Hydrogeology, Water Management              
----------------------------------------------------------------------------
Martin                                                                      
Williams, BSc.                                                              
PhD Tobias                                                                  
Roetting, BSc.  Schlumberger                                                
PhD             Water Services  Geochemistry                                
----------------------------------------------------------------------------
                                Executive Summary, Introduction, Reliance on
                                Other Experts, Property Description,        
                                Accessibility, Physiography, History,       
                                Infrastructure, Market Studies, Capital and 
                                Operating Costs, Economic Analysis, Adjacent
Wayne Corso,    JDS Energy &    properties, Interpretation and Conclusions, 
P.E.            Mining Inc.     Recommendations, References                 
----------------------------------------------------------------------------
                                                                            

This press release has been reviewed and approved by Donald Gray, BSc. Mining Engineering and MSc. Civil Engineering, Chief Operating Officer of the Company and a QP under NI 43-101.

For additional technical information on the Buriticá project, please refer to the 2015 Technical Report, available on SEDAR at www.sedar.com.

About Continental Gold

Continental Gold Inc. is an advanced-stage exploration and development company with an extensive portfolio of 100%-owned gold projects in Colombia. Formed in April 2007, the Company -- led by an international management team with a successful track record of discovering and developing large high-grade gold deposits in Latin America -- is focused on advancing its high-grade Buriticá gold project to production.

Additional details on the Buriticá project and the rest of Continental's suite of gold exploration properties are available at www.continentalgold.com.

Corporate Presentation

The Company's corporate presentation has been updated to include the results of the FS and is available on the Company's website at www.continentalgold.com.

Forward-Looking Statements

This press release contains or refers to forward-looking information under Canadian securities legislation, including statements regarding the results of the feasibility study, including, but not limited to, gold price and exchange rate assumptions, cash flow forecasts, projected capital and operating costs, metal or mineral recoveries, mine life and production rates; the Company's potential plans and operating performance; the estimation of the tonnage, grades and content of deposits, and the extent of the resource and reserves estimates; potential production from and viability of the Company's properties; estimates of future production and operating costs; estimates of permitting submissions and timing; the timing and receipt of necessary permits and project approvals for future operations; access to project funding, exploration results, and expected filing of the feasibility study technical report, and is based on current expectations that involve a number of business risks and uncertainties. Forward-looking statements are subject to significant risks and uncertainties, and other factors that could cause actual results to differ materially from expected results. Readers should not place undue reliance on forward-looking statements. Factors that could cause actual results to differ materially from any forward-looking statement include, but are not limited to, failure to convert estimated mineral resources to reserves, capital and operating costs varying significantly from estimates, the preliminary nature of metallurgical test results, delays in obtaining or failures to obtain required governmental, environmental or other project approvals, political risks, uncertainties relating to the availability and costs of financing needed in the future, changes in equity markets, inflation, changes in exchange rates, fluctuations in commodity prices, delays in the development of projects and the other risks involved in the mineral exploration and development industry. The forward-looking statements contained in this press release are made as of the date hereof and the Company assumes no responsibility to update them or revise them to reflect new events or circumstances other than as required by law.

Differences in Reporting of Resource Estimates

This press release was prepared in accordance with Canadian standards, which differ in some respects from United States standards. In particular, and without limiting the generality of the foregoing, the terms "inferred mineral resources," "indicated mineral resources," "measured mineral resources" and "mineral resources" used or referenced in this press release are Canadian mining terms as defined in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects under the guidelines set out in the Canadian Institute of Mining, Metallurgy and Petroleum (the "CIM") Standards on Mineral Resources and Mineral Reserves (the "CIM Standards"). The CIM Standards differ significantly from standards in the United States. While the terms "mineral resource," "measured mineral resources," "indicated mineral resources," and "inferred mineral resources" are recognized and required by Canadian regulations, they are not defined terms under standards in the United States. "Inferred mineral resources" have a great amount of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an inferred mineral resource will ever be upgraded to a higher category. Under Canadian securities laws, estimates of inferred mineral resources may not form the basis of feasibility or other economic studies. Readers are cautioned not to assume that all or any part of measured or indicated mineral resources will ever be converted into reserves. Readers are also cautioned not to assume that all or any part of an inferred mineral resource exists, or is economically or legally mineable. Disclosure of "contained ounces" in a resource is permitted disclosure under Canadian regulations; however, United States companies are only permitted to report mineralization that does not constitute "reserves" by standards in the United States as in place tonnage and grade without reference to unit measures. Accordingly, information regarding resources contained or referenced in this press release containing descriptions of our mineral deposits may not be comparable to similar information made public by United States companies.

For further information, please contact:
Paul Begin
Chief Financial Officer
Continental Gold Inc.
+1.416.583.5610
info@continentalgold.com
www.continentalgold.com


Legal Disclaimer:

EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.