Wind Powering America Case Study: Town of Hempstead Wind Turbine

Date: 6/3/2013

Wind Powering America interviewed Tara Schneider Moran, a conservation biologist for the Department of Conservation & Waterways in the Town of Hempstead, New York, to learn more about the wind turbine project in this community.

On December 12, 2011, the Town of Hempstead commissioned a Northern Power 100-kilowatt (kW) wind turbine to provide power to Long Island's only hydrogen-fueling station, where hydrogen fuel is generated on-site with an electrolyzer. The turbine cost $615,000, including design and installation, and was paid for as part of a $4.6 million U.S. Department of Energy (DOE) Energy Efficiency and Conservation Block Grant (from the 2009 American Recovery & Reinvestment Act) to the Town of Hempstead. The remaining funding was used for other energy efficiency and renewable energy projects, including multiple solar projects and a geothermal project.

The turbine generated more than 128,000 kilowatt-hours (kWh) in the 24 weeks after installation. One year after the commissioning date, after surviving Hurricane Sandy and approximately 1 month of down time due to grid issues (from both Sandy and other grid-related events), the turbine's total energy production was ~225,000 kWh. Its long-term projected range is between 180,000 and 240,000 kWh annually.

The annual energy cost savings for the Hempstead turbine are estimated at $40,000 for the local Long Island Power Authority (LIPA). LIPA is a local, non-profit municipal authority. Excess energy generated by the turbine will be returned to the LIPA grid, resulting in yet-to-be determined reductions in net electrical costs from the utility.

After a significant storm, it's important to inspect turbines and ensure their structural integrity. After Hurricane Sandy, the installer inspected the Hempstead turbine and found only one minor issue: the unit's compass was off and needed to be re-calibrated.

According to Moran, town officials are happy with the results of the curent turbine project and are now investigating the possibility of building a microgrid to make use of the turbine's energy production capabilities during future grid power interruptions.

Legal Disclaimer:

EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.